November 22, 2024 7:57 am

The premier news source for Snohomish County

Full closures of 46th Ave and 200th St in Lynnwood next week

LYNNWOOD—Construction Crews working on the Lynnwood Link Extension will be potholing, grinding, and paving roads near Lynnwood Transit Center resulting in closures as early as Monday, July 29.

Lynnwood Transit Center
Lynnwood Transit Center. Lynnwood Times | Mario Lotmore.

Full closures of 200th St SW between 50th Ave W and 44th Ave W in Lynnwood

As early as Monday, July 29, Sound Transit’s contractor will continue road work on 200th St SW for grinding and paving. This will require two separate full closures of 200th St SW between 50th Ave W and 44th Ave W. Detours will be provided (see maps) and police officers will be on-site to direct traffic and ensure local access is maintained.

200th St SW from 48th Ave W to 44th Ave W:

  • Monday, July 29.
  • Thursday, Aug. 1 – Friday, Aug. 2, all day and all night
Lynnwood closures

200th St SW from 50th Ave W to 48th Ave W:

  • Tuesday, July 30 – Wednesday, July 31, all day and all night.
Lynnwood closures

Full closure of 46th Ave W, south of 200th St SW

As early as Thursday, Aug. 1, Sound Transit’s contractor will continue potholing at 46th Ave W. This will require the closure of 46th Ave W south of 200th St SW and the HOV ramp from the Lynnwood Transit Center. Detours will be provided (see map). The contractor has received a temporary noise variance to complete this work.

46th Ave W, south of 200th St SW:

  • Thursday, Aug. 1, 11 p.m. – 5 a.m. the following morning
Lynnwood closures
Lynnwood closures
Mario Lotmore
Author: Mario Lotmore

Leave a Reply

Your email address will not be published. Required fields are marked *

Tell Us What You Think

This poll is no longer accepting votes

If you are IAM member, will you vote to approve the October 19 tentative agreement with Boeing? Poll ends 11:59 p.m., Oct 22, 2024.
VoteResults

    Join Our Mailing List

    Verified by MonsterInsights